ANALISA WHAT IF SEBAGAI METODE ANTISIPASI KETERLAMBATAN DURASI PROYEK

Main Author: Alifen, Ratna S; Faculty of Civil Engineering and Planning, Petra Christian University
Format: Article info application/pdf eJournal
Bahasa: eng
Terbitan: Institute of Research and Community Outreach - Petra Christian University , 2004
Subjects:
Online Access: http://ced.petra.ac.id/index.php/civ/article/view/15513
http://ced.petra.ac.id/index.php/civ/article/view/15513/15505
ctrlnum article-15513
fullrecord <?xml version="1.0"?> <dc schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/ http://www.openarchives.org/OAI/2.0/oai_dc.xsd"><title lang="en-US">ANALISA WHAT IF SEBAGAI METODE ANTISIPASI KETERLAMBATAN DURASI PROYEK</title><creator>Alifen, Ratna S; Faculty of Civil Engineering and Planning, Petra Christian University</creator><subject lang="en-US">Project delay, project accelaration, CPM scheduling, &#x201C;what if&#x201D; analysis, float</subject><description lang="en-US">A project network is composed of various activities interrelated in a sequencial relationship. If delay occurs on one activity, it will eventually cause the project overall duration to delay. To anticipate the project delays one could accelarate the succeeding activity in the network. Critical Path Method (CPM) is a management tool which is widely used in the construction project. In this study &#x201C;what if&#x201D; analysis is used to anticipate project delays by accelarating the activities on CPM schedule. The accelaration actions are treated in accordance with additional working hours and man-power in the succeeding activities Abstract in Bahasa Indonesia : Jaringan kerja proyek terdiri dari berbagai jenis aktivitas yang saling berkaitan antara satu dengan yang lain. Bila terjadi keterlambatan pada salah satu jenis aktivitas, sering kali akan menyebabkan keterlambatan durasi proyek secara keseluruhan. Salah satu usaha untuk mengantisipasi keterlambatan durasi proyek adalah dengan melakukan percepatan durasi aktivitas pengikut. Metode Jalur Kritis atau Critical Path Method (CPM) merupakan suatu metode penjadwalan proyek yang sudah dikenal dan sering digunakan sebagai sarana manajemen dalam pelaksanaan proyek. Sebuah studi telah dilakukan untuk mengatasi masalah percepatan durasi aktivitas sebagai langkah antisipasi keterlambatan proyek, dengan analisa &#x201C;what if&#x201D; yang diterapkan pada jadwal CPM. Percepatan durasi dilakukan pada aktivitas-aktivitas pengikut dengan menambah jumlah jam kerja dan jumlah pekerja pada aktivitas percepatan</description><publisher lang="en-US">Institute of Research and Community Outreach - Petra Christian University</publisher><date>2004-06-01</date><type>Journal:Article</type><type>Other:info:eu-repo/semantics/publishedVersion</type><type>File:application/pdf</type><identifier>http://ced.petra.ac.id/index.php/civ/article/view/15513</identifier><identifier>10.9744/ced.1.2.pp. 103-113</identifier><source lang="en-US">Civil Engineering Dimension; Vol 1, No 2 (1999): SEPTEMBER 1999; pp. 103-113</source><language>eng</language><relation>http://ced.petra.ac.id/index.php/civ/article/view/15513/15505</relation><rights>Authors who publish with this journal agree to the following terms: Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access). &#xA0; </rights><recordID>article-15513</recordID></dc>
language eng
format Journal:Article
Journal
Other:info:eu-repo/semantics/publishedVersion
Other
File:application/pdf
File
Journal:eJournal
author Alifen, Ratna S; Faculty of Civil Engineering and Planning, Petra Christian University
title ANALISA WHAT IF SEBAGAI METODE ANTISIPASI KETERLAMBATAN DURASI PROYEK
publisher Institute of Research and Community Outreach - Petra Christian University
publishDate 2004
topic Project delay
project accelaration
CPM scheduling
“what if” analysis
float
url http://ced.petra.ac.id/index.php/civ/article/view/15513
http://ced.petra.ac.id/index.php/civ/article/view/15513/15505
contents A project network is composed of various activities interrelated in a sequencial relationship. If delay occurs on one activity, it will eventually cause the project overall duration to delay. To anticipate the project delays one could accelarate the succeeding activity in the network. Critical Path Method (CPM) is a management tool which is widely used in the construction project. In this study “what if” analysis is used to anticipate project delays by accelarating the activities on CPM schedule. The accelaration actions are treated in accordance with additional working hours and man-power in the succeeding activities Abstract in Bahasa Indonesia : Jaringan kerja proyek terdiri dari berbagai jenis aktivitas yang saling berkaitan antara satu dengan yang lain. Bila terjadi keterlambatan pada salah satu jenis aktivitas, sering kali akan menyebabkan keterlambatan durasi proyek secara keseluruhan. Salah satu usaha untuk mengantisipasi keterlambatan durasi proyek adalah dengan melakukan percepatan durasi aktivitas pengikut. Metode Jalur Kritis atau Critical Path Method (CPM) merupakan suatu metode penjadwalan proyek yang sudah dikenal dan sering digunakan sebagai sarana manajemen dalam pelaksanaan proyek. Sebuah studi telah dilakukan untuk mengatasi masalah percepatan durasi aktivitas sebagai langkah antisipasi keterlambatan proyek, dengan analisa “what if” yang diterapkan pada jadwal CPM. Percepatan durasi dilakukan pada aktivitas-aktivitas pengikut dengan menambah jumlah jam kerja dan jumlah pekerja pada aktivitas percepatan
id IOS3114.article-15513
institution Universitas Kristen Petra Surabaya
institution_id 48
institution_type library:university
library
library Perpustakaan Universitas Kristen Petra Surabaya
library_id 533
collection Civil Engineering Dimension
repository_id 3114
subject_area Rekayasa
city KOTA SURABAYA
province JAWA TIMUR
repoId IOS3114
first_indexed 2016-09-23T02:34:06Z
last_indexed 2016-09-23T02:34:06Z
recordtype dc
merged_child_boolean 1
_version_ 1722504830908366848
score 17.60506