Analisa Keterlambatan Proses Reparasi Kapal KM Dharma Ferry 9 Menggunakan Metode Time Cost Trade Off

Main Authors: Herdianti, Winda Amalia, Prasetyawati, Dian, Setiawan, Maulidi
Format: Article info application/pdf Journal
Bahasa: ind
Terbitan: Universitas Muhammadiyah Surabaya Publishing , 2023
Subjects:
Online Access: https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087
https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087/7396
ctrlnum article-19087
fullrecord <?xml version="1.0"?> <dc schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/ http://www.openarchives.org/OAI/2.0/oai_dc.xsd"><title lang="id-ID">Analisa Keterlambatan Proses Reparasi Kapal KM Dharma Ferry 9 Menggunakan Metode Time Cost Trade Off</title><creator>Herdianti, Winda Amalia</creator><creator>Prasetyawati, Dian</creator><creator>Setiawan, Maulidi</creator><subject lang="id-ID">analisa keterlambatan</subject><subject lang="id-ID">analisa keterlambatan</subject><description lang="id-ID">Reparasi kapal di galangan sangat penting untuk dilakukan karena tidak semua perbaikan dapat dilakukan di atas perairan khususnya jenis pekerjaan di bawah garis air. Dalam proses pembuatan, kapal harus melakukan docking di galangan kapal sehingga perlu dibuatkan jadwal perbaikan atau repair list agar proyek reparasi berjalan sesuai harapan. Namun permasalahan teknis maupun non teknis terkadang&#xA0; membuat jadwal perbaikan di atas galangan menjadi lebih lama dari perkiraan awal sehingga harus dilakukan penelitian agar penyebab keterlambatan dapat diketahui dan mencari solusi untuk meminimalkan keterlambatan tersebut menggunakan metode perhitungan time cost trade off . Metode time cost trade off adalah metode dengan&#xA0; menentukan penambahan jam kerja (lembur) maupun penambahan main power agar jadwal kapal di atas galangan seminimal mungkin mengalami keterlambatan dalam proyek reparasi tersebut. Dalam projek ini keterlambatan terjadi karena adanya keterlambatan material&#xA0; dan dengan adanya simulasi dari metode ini, hasil terbaik yang didapatkan ialah projek menambahkan pekerja yang tadinya 8 menjadi 14 orang.</description><publisher lang="id-ID">Universitas Muhammadiyah Surabaya Publishing</publisher><date>2023-12-28</date><type>Journal:Article</type><type>Other:info:eu-repo/semantics/publishedVersion</type><type>Journal:Article</type><type>File:application/pdf</type><identifier>https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087</identifier><identifier>10.30651/mine-tech.v2i2.19087</identifier><source lang="id-ID">MINE-TECH: Journal of Manufacturing in Industrial Engineering &amp; Technology; Vol 2 No 2 (2023): Journal of Manufacturing in Industrial Engineering &amp; Technology; 10 - 19</source><source>2985-3516</source><source>10.30651/mine-tech.v2i2</source><language>ind</language><relation>https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087/7396</relation><rights lang="id-ID">Hak Cipta (c) 2023 Winda Amalia Herdianti, Dian Prasetyawati, Maulidi Setiawan</rights><rights lang="id-ID">https://creativecommons.org/licenses/by/4.0</rights><recordID>article-19087</recordID></dc>
language ind
format Journal:Article
Journal
Other:info:eu-repo/semantics/publishedVersion
Other
File:application/pdf
File
Journal:Journal
author Herdianti, Winda Amalia
Prasetyawati, Dian
Setiawan, Maulidi
title Analisa Keterlambatan Proses Reparasi Kapal KM Dharma Ferry 9 Menggunakan Metode Time Cost Trade Off
publisher Universitas Muhammadiyah Surabaya Publishing
publishDate 2023
topic analisa keterlambatan
url https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087
https://journal.um-surabaya.ac.id/MINE-TECH/article/view/19087/7396
contents Reparasi kapal di galangan sangat penting untuk dilakukan karena tidak semua perbaikan dapat dilakukan di atas perairan khususnya jenis pekerjaan di bawah garis air. Dalam proses pembuatan, kapal harus melakukan docking di galangan kapal sehingga perlu dibuatkan jadwal perbaikan atau repair list agar proyek reparasi berjalan sesuai harapan. Namun permasalahan teknis maupun non teknis terkadang membuat jadwal perbaikan di atas galangan menjadi lebih lama dari perkiraan awal sehingga harus dilakukan penelitian agar penyebab keterlambatan dapat diketahui dan mencari solusi untuk meminimalkan keterlambatan tersebut menggunakan metode perhitungan time cost trade off . Metode time cost trade off adalah metode dengan menentukan penambahan jam kerja (lembur) maupun penambahan main power agar jadwal kapal di atas galangan seminimal mungkin mengalami keterlambatan dalam proyek reparasi tersebut. Dalam projek ini keterlambatan terjadi karena adanya keterlambatan material dan dengan adanya simulasi dari metode ini, hasil terbaik yang didapatkan ialah projek menambahkan pekerja yang tadinya 8 menjadi 14 orang.
id IOS20313.article-19087
institution Universitas Muhammadiyah Surabaya
institution_id 761
institution_type library:university
library
library Perpustakaan Universitas Muhammadiyah Surabaya
library_id 880
collection MINE-TECH: Journal of Manufacturing in Industrial Engineering & Technology
repository_id 20313
subject_area Supply Chain & Logistic, Operations Research, Planning & Scheduling, Quality & Reliability, Industrial Food, Halal Industry
Enterprise Engineering, Project Management, Energy & Environmental, Occupational Hafety and Health, System & Digital Manufacturing
Decision Analysis, Computational Intelligence, Data Mining
Healthcare, Medic System
city KOTA SURABAYA
province JAWA TIMUR
repoId IOS20313
first_indexed 2024-06-14T06:20:54Z
last_indexed 2024-06-14T06:20:54Z
recordtype dc
_version_ 1801816537824231424
score 9.9049015