1 x 125 mw coal fired steam power plant economic analysis at pt krakatau daya listrik

Main Authors: Anggraeni, Dian, Murtaqi, Isrochmani
Format: Article info eJournal
Bahasa: eng
Terbitan: The Indonesian Journal of Business Administration , 2019
Online Access: https://journal.sbm.itb.ac.id/index.php/IJBA/article/view/3244
ctrlnum article-3244
fullrecord <?xml version="1.0"?> <dc schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/ http://www.openarchives.org/OAI/2.0/oai_dc.xsd"><title lang="en-US">1 x 125 mw coal fired steam power plant economic analysis at pt krakatau daya listrik</title><creator>Anggraeni, Dian</creator><creator>Murtaqi, Isrochmani</creator><description lang="en-US">Abstract. This study aims to perform an economic feasibility analysis of the construction project of Coal Fired Steam Power Plant with 125 MW capacities to be performed by PT Krakatau Daya Listrik, a subsidiary company from PT Krakatau Steel This research will analyze whether an investment on the construction of Coal Fired Steam Power Plant with 125 MW capacity is financially feasible. The analysis is conducted by using Capital budgeting method through Discounted Cash Flow approach. Indicators measured are Net Present Value, Internal Rate of Return, Payback Period. In this approach also carried out the project sensitivity analysis. The construction project of a 1 x 125 MW Coal Fired Steam Power Plant is financially feasible by comparing financial feasibility parameters such as Net Present Value (NPV)&amp;gt; 0, Internal Rate of Return (IRR)&amp;gt; Cost of Capital and Payback Period less than maximum payback period that can be accepted. Based on the results of the analysis of these parameters, the construction project of Coal Fired Steam Power Plant 1 x 125 MW is feasible to be done financially with NPV value of MIDR 2,345,451, IRR 13.76% larger than WACC of 8.07% and Payback Period for 6 years 3 months. In relation to the results of financial analysis, the sensitivity analysis is used to determine the feasibility characteristics of the project on changes in investment value caused by the influence of economic variables and technical parameters. To conduct a deeper analysis, it is necessary to calculate the investment indicators by making changes (sensitivity analysis) to the key parameters that influence: EPC cost, coal price, loan interest rate, change in exchange rate and electricity tariff.Keywords: Capital Budgeting, Net Present Value, Internal Rate of Return, Payback Period, Sensitivity Analysis.</description><publisher lang="en-US">The Indonesian Journal of Business Administration</publisher><contributor lang="en-US"/><date>2019-09-08</date><type>Journal:Article</type><type>Other:info:eu-repo/semantics/publishedVersion</type><type>Journal:Article</type><identifier>https://journal.sbm.itb.ac.id/index.php/IJBA/article/view/3244</identifier><source lang="en-US">The Indonesian Journal of Business Administration; Vol 7, No 3 (2018)</source><source>2252-9284</source><source>2252-3464</source><language>eng</language><recordID>article-3244</recordID></dc>
language eng
format Journal:Article
Journal
Other:info:eu-repo/semantics/publishedVersion
Other
Journal:eJournal
author Anggraeni, Dian
Murtaqi, Isrochmani
title 1 x 125 mw coal fired steam power plant economic analysis at pt krakatau daya listrik
publisher The Indonesian Journal of Business Administration
publishDate 2019
url https://journal.sbm.itb.ac.id/index.php/IJBA/article/view/3244
contents Abstract. This study aims to perform an economic feasibility analysis of the construction project of Coal Fired Steam Power Plant with 125 MW capacities to be performed by PT Krakatau Daya Listrik, a subsidiary company from PT Krakatau Steel This research will analyze whether an investment on the construction of Coal Fired Steam Power Plant with 125 MW capacity is financially feasible. The analysis is conducted by using Capital budgeting method through Discounted Cash Flow approach. Indicators measured are Net Present Value, Internal Rate of Return, Payback Period. In this approach also carried out the project sensitivity analysis. The construction project of a 1 x 125 MW Coal Fired Steam Power Plant is financially feasible by comparing financial feasibility parameters such as Net Present Value (NPV)&gt; 0, Internal Rate of Return (IRR)&gt; Cost of Capital and Payback Period less than maximum payback period that can be accepted. Based on the results of the analysis of these parameters, the construction project of Coal Fired Steam Power Plant 1 x 125 MW is feasible to be done financially with NPV value of MIDR 2,345,451, IRR 13.76% larger than WACC of 8.07% and Payback Period for 6 years 3 months. In relation to the results of financial analysis, the sensitivity analysis is used to determine the feasibility characteristics of the project on changes in investment value caused by the influence of economic variables and technical parameters. To conduct a deeper analysis, it is necessary to calculate the investment indicators by making changes (sensitivity analysis) to the key parameters that influence: EPC cost, coal price, loan interest rate, change in exchange rate and electricity tariff.Keywords: Capital Budgeting, Net Present Value, Internal Rate of Return, Payback Period, Sensitivity Analysis.
id IOS2616.article-3244
institution Institut Teknologi Bandung
affiliation onesearch.perpusnas.go.id
institution_id 79
institution_type library:university
library
library Perpustakaan Institut Teknologi Bandung
library_id 100
collection The Asian Journal of Technology Management (AJTM)
repository_id 2616
city KOTA BANDUNG
province JAWA BARAT
repoId IOS2616
first_indexed 2019-09-21T15:00:19Z
last_indexed 2019-09-21T15:00:19Z
recordtype dc
merged_child_boolean 1
_version_ 1685803027534970880
score 17.60897